Front End Engineering
Consultancy
ContactorFlash Sep.Still Col.ReboilerDry Gas
All projectsOnshore · Package Design

Glycol Gas Dehydration Skid — Tender Support

Process SimulationConceptual EngineeringTender Support

Project Overview

Tender engineering for a skid-mounted TEG gas dehydration unit targeting a 7 lb/MMscfd sales gas water content specification, sized for 25 MMscfd at 60 bara operating pressure.

Technical Scope

Capacity
25 MMscfd
Operating pressure
60 bara
Water spec
7 lb/MMscfd
Tender window
4 weeks
Client
Confidential

Engineering Approach

A full process simulation, contactor and regeneration still column sizing, glycol circulation pump and heat exchanger design were completed within a four-week tender window, supporting a competitive technical submission.

The complete equipment datasheet package — contactor vessel, reboiler, glycol-glycol heat exchanger, and flash separator — was issued with a structured process design narrative giving the client a fully substantiated equipment basis for commercial bidding.

Have a similar scope? Tell us your project and we'll respond within one business day.

Discuss your project

Project Outcomes

  • Tender submission delivered within the four-week window
  • Technical compliance confirmed by client's engineering review
  • Tender subsequently awarded to the client

Services Delivered

Process SimulationConceptual EngineeringTender Support